Consultancy Services for Authority's Engineer for Supervision of Four Laning of Madurai- Chettikulam Section of Nh-785 from Madurai (Km 0/000) to Chettikulam (7/300) under Bharatmala Pariyojna Phase-I in the State of Tamil Nadu on EPC mode.
The Project Highway comprises of construction of 4-lane elevated highway and ground level improvement. The elevated highway shall include 4-lane divided carriageway, 2-lane carriageways on Gokahle road, Alagar Koil road and Mattuthavani road. Service roads shall be constructed at a design length of 7.3 km on both sides.
- Elevated highway (Grade Separated structures) = 8
Superstructure Type- PSC Segmental Box Girder
- Arm-1: Gokhale road Ch. 0+000 to 0+273
Total Length= 273m - Arm-2: Alagar Koil
Total Length= 360m - Arm-3: Mattuthavani
Total Length= 252m - 4-lane Elevated Corridor
Total Length= 7.573m
- Arm-1: Gokhale road Ch. 0+000 to 0+273
- Intersection of five urban roads (Major/Minor) = 10
- Reconstruction of RCC Box culverts = 17
Total length= 7105m - Reconstruction of Bridges = 1
Span= 2x8.0 - Four-lane paved carriageway shall be provided as indicated below:
- Arm-1, Arm-2, Arm-3 = 7.5m
- NH:785 (Natham road) = 2x7.50m
- Entry/Exit via-duct ramps and solid ramps = 6m
About 300 piers are in progress of construction and artistic work will also to be carried out.